Construction Update WIS 20

CONSTRUCTION UPDATE-
07-10-2024
Hello,
The County ES closure date has been moved to Wednesday, July 17th. This change is to help better position the contractor’s resources to try and shave whatever days we can off the 21-day closure. The message boards on County ES will be updated today/tonight to show the new date. Attached is the updated construction flyer showing the changes.
Elsewhere, work has picked up. Road excavation in East Troy is ongoing and will roll into the County ES closure next week. Between County L and Waterford, we started removing the trees/stumps cut last fall, existing guardrail, and installed some of the erosion control devices. The operations will continue to pick up and hopefully we catch some dry days going forward.
The intersection of WIS 20 and County L will be done in halves to allow traffic to continue to use County L. While this may cause a few small delays, we are trying to avoid using a 14-day closure of the intersection to complete the work. With the north leg of County ES being closed next week, County L needs to remain open to offer an alternate route for traffic.
WIS 20 (East Troy)
Traffic:
1) Access to Bower’s Produce can be made by continuing east on WIS 20 from County L (East Troy)
2) Access to Green Meadows can be made by going west on WIS 20 from WIS 83 (Waterford)
3) Access to Kwik Trip during the County ES closure will be using County ES coming from the Mukwonago direction (North).
4) Access to Culver’s when it opens on 7/22 will be by using WIS 20.
This Week:
1) Roadway excavation and rock placement
Next Week:
1) Continue roadway excavation and rock placement.
2) County ES north leg closure – begin pavement removals and storm sewer
WIS 20 – County L to WIS 83 (Waterford)
Traffic:
1) Access to Bower’s Produce can be made by continuing east on WIS 20 from County L (East Troy)
2) Access to Green Meadows can be made by going west on WIS 20 from WIS 83 (Waterford)
3) Access to Witte Landscaping can be made by going west on WIS 20 from WIS 83 (Waterford)
4) Once the guardrail is removed on WIS 20 along Honey Creek/County Line area, the barricades on either side of the “Fully Closed” section will be tightly closed as the roadway is no longer safe to allow vehicles through (other than EMS).
This Week:
1) Remove the trees/stumps cut last fall
2) Install erosion control devices along Honey Creek.
3) Remove existing guardrail
Next Week:
1) Continue erosion control devices installation
2) Begin installation of storm sewer by the retaining wall
Information on the other WisDOT project up on I-43 from US 12 to WIS 83 is below:
Information on the US 12 project between Elkhorn and WIS 20: