Work started back up in the WIS 20/County ES intersection for the concrete medians. The crew is expected back on site tomorrow to hopefully finish up. The last operation prior to removing all the drums west of County L is some guardrail work under the I-43 bridges. That work is scheduled for Tuesday/Wednesday so if the weather cooperates, we should be pulling drums late next week.
The work for the culvert east of Carver School Rd is scheduled for November 4th. This will result in a closure of WIS 20 between Carver School and Hillburn Mill Rd for about a week while we replace the culvert. We will have message boards directing traffic around the closure to help keep local access.
Attached is a local detour map to navigate the closure by Carver School Rd.
East Troy – WIS 20/County ES intersection
- Finish up the concrete islands in the intersection
WIS 20 – Bell School Road to Honey Creek Rd (County Line area)
- This part of the project will decide when we are able to re-open WIS 20 between East Troy and Waterford. Below are the remaining operations that need to occur.
- Install Pavement Markings and Signage (Week of 11/4 but weather dependent)
WIS 20 (East Troy)
Traffic:
- Access to Bower’s Produce can be made by continuing east on WIS 20 from County L (East Troy)
- Access to Green Meadows can be made by going west on WIS 20 from WIS 83 (Waterford)
- Access to Culver’s will be by using WIS 20.
This Week:
- Started the concrete islands in the WIS 20/County ES intersection
Next Week:
- Pour and completed the concrete islands in the intersection.
- Begin removing some drums and barricades.
WIS 20 – County L to WIS 83 (Waterford) Traffic:
- Access to Bower’s Produce can be made by continuing east on WIS 20 from County L (East Troy)
- Access to Green Meadows can be made by going west on WIS 20 from WIS 83 (Waterford)
- Access to Witte Landscaping can be made by going west on WIS 20 from WIS 83 (Waterford)
This Week:
- Guardrail installation
- Rumble Strips
- Started Pavement Markings
Next Week:
- Complete pavement markings and signing
If you do not want to receive these updates, please let me know and I can remove you from the distribution list. Also, WisDOT has a project website set up for information that is more general than this email but could be useful if needed. https://projects.511wi.gov/20wal/
If you have any other questions or comment, please continue to reach out.