Construction Update WIS 20: Asphalt paving has moving along this week from Honey Creek Rd to WIS 83. That should be wrapped up on Monday and Tuesday the crews will move to the area between County L and Bell School. We have a few patches to fix up and those will be completed on Monday.   In East Troy we started shouldering and topsoil placement. Pavement marking and signage is scheduled for next week along with signal work. Having the markings and signing installed will allow traffic on WIS 20 to be put back on the correct side of the median and have the I-43 ramps re-opened.   I-43 Ramps at WIS 20 – Scheduled to re-opened on Monday, September 16th. Not sure on the exact time of day yet but will be included in next weeks update.     WIS 20 (East Troy) Traffic: Access to Bower’s Produce can be made by continuing east on WIS 20 from County L (East Troy) Access to Green Meadows can be made by going west on WIS 20 from WIS 83 (Waterford) Access to Culver’s will be by using WIS 20.   This Week: Shouldering along WIS 20 Topsoil placement   Next Week: Continue Topsoiling/grading Pavement markings Seeding/restoration   WIS 20 - County L to WIS 83 (Waterford) Traffic: Access to Bower’s Produce can be made by continuing east on WIS 20 from County L (East Troy) Access to Green Meadows can be made by going west on WIS 20 from WIS 83 (Waterford) Access to Witte Landscaping can be made by going west on WIS 20 from WIS 83 (Waterford)   This Week: Asphalt paving from Honey Creek Road to WIS 83 Completed milling operations removing the top 2” of asphalt   Next Week: Complete asphalt paving from Honey Creek Rd to WIS 83 Begin asphalt paving from County L to Bell School Rd on Tuesday Begin working on the retaining wall   Long Term (2+weeks) Complete asphalt paving Complete the retaining wall Install rumble strips Install pavement markings Install signing   Information on the other WisDOT project up on I-43 from US 12 to WIS 83 is below: https://projects.511wi.gov/12rock/   Information on the US 12 project between Elkhorn and WIS 20: https://projects.511wi.gov/12elkhorn/     If you do not want to receive these updates, please let me know and I can remove you from the distribution list. Also, WisDOT has a project website set up for information that is more general than this email but could be useful if needed. https://projects.511wi.gov/20wal/  

Construction Update STH 120

Project work last week included:

  • Sawcutting concrete, removing concrete, and preparing for concrete patches on STH 120 from Honey Creek Road to the south limit of the concrete section.
  • Concrete pavement repairs/patching on STH 120 from Honey Creek Road to the south limit of the concrete section.
  • Finished placing concrete panels for the retaining wall south of Swoboda Road.
  • Continued working on concrete repairs on the girders of the interstate bridges.

 

Project work happening this week:

  • Removing pavement for the new right turn lane and acceleration lane at STH 36.
  • Grade for new pavement at STH 36.
  • Sawcutting concrete, removing concrete, and preparing for concrete patches on STH 120 from Honey Creek Road to NB IH-43 Ramps.
  • Concrete pavement repairs/patching on STH 120 from Honey Creek Road to NB IH-43 Ramps.
  • Remove existing guard rail and place new gravel for new rails.
  • Install new guard rail throughout STH 120.
  • Removing existing curb in Springfield and prepare for concrete work.
  • Pour concrete curb and gutter in Springfield.
  • Pour concrete coping on new concrete wall blocks.
  • Grading behind new retaining wall.

 

Traffic changes happening in the next 7 days: (Reminder that you can check out WIS 120 Rehabilitation – Walworth County (511wi.gov) for updates and help navigating the construction zones in the area.)

  • Road closed to all traffic from Honey Creek Road to the northbound ramps for IH-43 in both directions of travel from Monday August 28th 6:00 AM to Friday September 1st 12:00 PM.  The shutdown is required to remove damaged concrete pavement and replace it.  Due to the nature of concrete work and how long concrete takes to set, the closure may extend beyond 12:00 PM on September 1st, but all attempts to open the roadway by that time will be made.  Residential and business traffic WILL NOT BE ABLE TO GET THROUGH CLOSED SEGMENT.  Please plan accordingly.
  • Road closed to all traffic is set to begin on Tuesday September 5th 6:00 AM through Thursday September 7th 10:00 PM from the IH-43 NB Entrance Ramp to the IH-43 SB Entrance and Exit Ramps, along with the NB IH-43 Exit Ramp to STH 120.  Residential and business traffic WILL NOT BE ABLE TO GET THROUGH CLOSED SEGMENT.  Please plan accordingly.

 

**I have attached a copy of the hard closure schedule with visuals for what will be accessible and what will not be.**