Generic selectors
Exact matches only
Search in title
Search in content
Post Type Selectors

Construction Update WIS 20: Asphalt paving has moving along this week from Honey Creek Rd to WIS 83. That should be wrapped up on Monday and Tuesday the crews will move to the area between County L and Bell School. We have a few patches to fix up and those will be completed on Monday.   In East Troy we started shouldering and topsoil placement. Pavement marking and signage is scheduled for next week along with signal work. Having the markings and signing installed will allow traffic on WIS 20 to be put back on the correct side of the median and have the I-43 ramps re-opened.   I-43 Ramps at WIS 20 – Scheduled to re-opened on Monday, September 16th. Not sure on the exact time of day yet but will be included in next weeks update.     WIS 20 (East Troy) Traffic: Access to Bower’s Produce can be made by continuing east on WIS 20 from County L (East Troy) Access to Green Meadows can be made by going west on WIS 20 from WIS 83 (Waterford) Access to Culver’s will be by using WIS 20.   This Week: Shouldering along WIS 20 Topsoil placement   Next Week: Continue Topsoiling/grading Pavement markings Seeding/restoration   WIS 20 - County L to WIS 83 (Waterford) Traffic: Access to Bower’s Produce can be made by continuing east on WIS 20 from County L (East Troy) Access to Green Meadows can be made by going west on WIS 20 from WIS 83 (Waterford) Access to Witte Landscaping can be made by going west on WIS 20 from WIS 83 (Waterford)   This Week: Asphalt paving from Honey Creek Road to WIS 83 Completed milling operations removing the top 2” of asphalt   Next Week: Complete asphalt paving from Honey Creek Rd to WIS 83 Begin asphalt paving from County L to Bell School Rd on Tuesday Begin working on the retaining wall   Long Term (2+weeks) Complete asphalt paving Complete the retaining wall Install rumble strips Install pavement markings Install signing   Information on the other WisDOT project up on I-43 from US 12 to WIS 83 is below: https://projects.511wi.gov/12rock/   Information on the US 12 project between Elkhorn and WIS 20: https://projects.511wi.gov/12elkhorn/     If you do not want to receive these updates, please let me know and I can remove you from the distribution list. Also, WisDOT has a project website set up for information that is more general than this email but could be useful if needed. https://projects.511wi.gov/20wal/  

Construction Update STH 120 09 19 2023

Thank you to everyone for your ongoing patience and understanding of the necessary closures to ensure your safety, and our safety.
Project work last week included:
• Sawcutting concrete, removing concrete, and preparing for concrete patches on STH 120 north of IH-43.
• Concrete pavement repairs/patching on STH 120 north of IH-43.
• Poured concrete curb & gutter, sidewalks, half of the trail’s concrete.
• Milling existing asphalt and paving new asphalt lower middle lift of mainline.
• Concrete girder repair on IH-43 bridges over STH 120.
• Finish pouring retaining wall coping.
Project work happening this week:
• Pour curb and gutter along MSE wall.
• Pour concrete sidewalk.
• Finish milling existing asphalt mainline and shoulder and continue paving new asphalt
• Concrete girder repair on IH-43 bridges over STH 120.
• Replacing aged bearing pad under the IH-43 bridges.
Traffic changes happening in the next 7 days: (Reminder that you can check out WIS 120 Rehabilitation – Walworth County (511wi.gov) for updates and help navigating the construction zones in the area.)
• Traffic switch on IH-43 NB and SB will be happening Tuesday at 9:00 AM. Work will be done to switch traffic from the current travel lane to the opposite side to finish work on the concrete on the bridges. A full width travel lane and shoulder will be maintained in both directions and will have little impact on travel over STH 120.
Bob Williamson
STH 120
Project Leader