Generic selectors
Exact matches only
Search in title
Search in content
Post Type Selectors

Construction Update WIS 20: Asphalt paving has moving along this week from Honey Creek Rd to WIS 83. That should be wrapped up on Monday and Tuesday the crews will move to the area between County L and Bell School. We have a few patches to fix up and those will be completed on Monday.   In East Troy we started shouldering and topsoil placement. Pavement marking and signage is scheduled for next week along with signal work. Having the markings and signing installed will allow traffic on WIS 20 to be put back on the correct side of the median and have the I-43 ramps re-opened.   I-43 Ramps at WIS 20 – Scheduled to re-opened on Monday, September 16th. Not sure on the exact time of day yet but will be included in next weeks update.     WIS 20 (East Troy) Traffic: Access to Bower’s Produce can be made by continuing east on WIS 20 from County L (East Troy) Access to Green Meadows can be made by going west on WIS 20 from WIS 83 (Waterford) Access to Culver’s will be by using WIS 20.   This Week: Shouldering along WIS 20 Topsoil placement   Next Week: Continue Topsoiling/grading Pavement markings Seeding/restoration   WIS 20 - County L to WIS 83 (Waterford) Traffic: Access to Bower’s Produce can be made by continuing east on WIS 20 from County L (East Troy) Access to Green Meadows can be made by going west on WIS 20 from WIS 83 (Waterford) Access to Witte Landscaping can be made by going west on WIS 20 from WIS 83 (Waterford)   This Week: Asphalt paving from Honey Creek Road to WIS 83 Completed milling operations removing the top 2” of asphalt   Next Week: Complete asphalt paving from Honey Creek Rd to WIS 83 Begin asphalt paving from County L to Bell School Rd on Tuesday Begin working on the retaining wall   Long Term (2+weeks) Complete asphalt paving Complete the retaining wall Install rumble strips Install pavement markings Install signing   Information on the other WisDOT project up on I-43 from US 12 to WIS 83 is below: https://projects.511wi.gov/12rock/   Information on the US 12 project between Elkhorn and WIS 20: https://projects.511wi.gov/12elkhorn/     If you do not want to receive these updates, please let me know and I can remove you from the distribution list. Also, WisDOT has a project website set up for information that is more general than this email but could be useful if needed. https://projects.511wi.gov/20wal/  

CONSTRUCTION UPDATE: 06 06 2024

Hello,

 

We are now fully into Stage 3 for the project. Please see attached for the signed detours, traffic staging plan, and some site photos from today. The new traffic configuration may take some time for residents, customers, and visitors to get used too. Please review the detour map as WIS 20 should only be used to access your residence or a business if their only access is by using WIS 20.

 

Although we do not have our hard closures set up at the CN railroad yet (they are expected to perform their work after July 4th), traffic should still not travel directly from East Troy to Waterford using WIS 20 (use signed detour or alternate route instead) as we will have crews out on the highway working. Also, we decided to leave WIS 20 for this stretch semi-open to help law enforcement and EMS services better serve the area until the road closure needs to occur.

 

WIS 20 (East Troy) – Moved into Stage 3

Traffic:

  1. Access to Bower’s Produce can be made by continuing east on WIS 20 from County L (East Troy)
  2. Access to Green Meadows can be made by going west on WIS 20 from WIS 83 (Waterford)

 

This Week:

  1. Complete switch into Stage 3
  2. Begin removal of the existing WIS 20 WB concrete

 

Next Week:

  1. Continue concrete removals
  2. Begin Storm Sewer installation

 

 

WIS 20 – County L to WIS 83 (Waterford)

Traffic:

  1. Access to Bower’s Produce can be made by continuing east on WIS 20 from County L (East Troy)
  2. Access to Green Meadows can be made by going west on WIS 20 from WIS 83 (Waterford)
  3. Access to Witte Landscaping can be made by going west on WIS 20 from WIS 83 (Waterford)

 

This Week:

  1. Complete switch into Stage 3
  2. Begin marking out the roadway patching areas

 

Next Week:

  1. Continue patch layout
  2. Begin saw cutting the patches

 

Information on the other WisDOT project up on I-43 from US 12 to WIS 83 is below:

https://projects.511wi.gov/12rock/

Information on the US 12 project between Elkhorn and WIS 20:

https://projects.511wi.gov/12elkhorn/